Lexus ES: Installation
INSTALLATION
PROCEDURE
1. INSTALL GENERATOR ASSEMBLY
(a) Install the generator assembly with the bolt and 2 nuts.
Torque:
25 N·m {255 kgf·cm, 18 ft·lbf}
(b) Engage the clamp.
(c) Connect the E.F.I. vacuum sensor assembly (manifold absolute pressure sensor) connector.
(d) Install the wire harness clamp bracket to the generator assembly with the bolt.
Torque:
10 N·m {102 kgf·cm, 7 ft·lbf}
(e) Connect the wire harness to terminal B with the nut.
Torque:
9.8 N·m {100 kgf·cm, 87 in·lbf}
(f) Close the terminal cap.
(g) Connect the generator assembly connector.
2. INSTALL V-RIBBED BELT
Click here
3. INSTALL INLET AIR CLEANER ASSEMBLY
Click here
4. INSTALL COOL AIR INTAKE DUCT SEAL
Click here
5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Click here
READ NEXT:
REASSEMBLY PROCEDURE 1. INSTALL GENERATOR ROTOR BEARING (a) Using SST and a press, install a new generator rotor bearing. SST: 09950-60011 09951-00470 SST: 09950-70010 09951-07100 (b
INSPECTION PROCEDURE 1. INSPECT GENERATOR BRUSH HOLDER ASSEMBLY (a) Using a vernier caliper, measure the length of the exposed brushes. Standard Exposed Brush Length: 9.5 to 11.5 mm (0.374 to 0.45
DISASSEMBLY PROCEDURE 1. REMOVE GENERATOR PULLEY CAP (a) Remove the generator pulley cap from the generator pulley with clutch. NOTICE:
Do not reuse the generator pulley cap.
If the generato
SEE MORE:
REMOVAL CAUTION / NOTICE / HINT The necessary procedures (adjustment, calibration, initialization, or registration) that must be performed after parts are removed and installed, or replaced during air fuel ratio sensor removal/installation are shown below. Necessary Procedures After Parts Removed/In
PROCEDURE 1. CHECK PORTABLE PLAYER SETTINGS (a) Check the portable player settings. (1) Check that the volume is not set to "0". (2) Check that mute is off. (b) Check that the sound of the portable player can be heard from the speakers. OK: Sound of the portable player can be heard from th
© 2016-2024 Copyright www.lexguide.net