1. INSTALL MOTOR CABLE
CAUTION:
Be sure to wear insulated gloves.
(a) Using an insulated tool, install the motor cable to the hybrid vehicle transaxle assembly with the 6 bolts.
Torque:
10 N·m {102 kgf·cm, 7 ft·lbf}
NOTICE:
-
Keep the motor cable terminals and their installation area free from foreign matter, water, etc.
-
Do not touch the waterproof seal or terminals of the motor cable.
(b) Engage the 2 claws to install a new terminal cap to the hybrid vehicle transaxle assembly.
NOTICE:
-
Keep the terminal cap and its installation area free from foreign matter, water, etc.
-
Do not pinch the O-ring.
-
Check that the terminal cap is securely installed.
(c) Temporarily install the connector cover to the hybrid vehicle transaxle assembly with the 2 bolts.
(d) Tighten the 2 bolts to install the connector cover.
Torque:
10 N·m {102 kgf·cm, 7 ft·lbf}
2. INSTALL INVERTER WITH CONVERTER ASSEMBLY
Click here
READ NEXT:
REMOVAL CAUTION / NOTICE / HINT The necessary procedures (adjustment, calibration, initialization, or registration) that must be performed after parts are removed and installed, or replaced during mot
COMPONENTS ILLUSTRATION *1 FRONT WHEEL OPENING EXTENSION PAD RH *2 FRONT WHEEL OPENING EXTENSION PAD LH *3 NO. 1 ENGINE UNDER COVER *4 NO. 2 ENGINE UNDER COVER ASSEMBLY *5 FR
SEE MORE:
INSPECTION PROCEDURE 1. INSPECT FLOW SHUTTING VALVE (NO. 1 WATER BY-PASS HOSE) (a) Measure the resistance according to the value(s) in the table below. Standard Resistance: Tester Connection Condition Specified Condition 1 - 2 20°C (68°F) 22 to 28 Ω If the result is not as spec
On-vehicle InspectionON-VEHICLE INSPECTION PROCEDURE 1. INSPECT H-LP LH RELAY (a) Measure the resistance according to the value(s) in the table below. Standard Resistance: Tester Connection Condition Specified Condition 3 - 5 Voltage not applied between terminals 1 and 2 10 kΩ or
© 2016-2026 Copyright www.lexguide.net