Lexus ES manuals

Lexus ES: Removal

REMOVAL

PROCEDURE

1. REMOVE FRONT WHEEL OPENING EXTENSION PAD LH

for A25A-FKS: Click here

for A25A-FXS: Click here

for 2GR-FKS: Click here

2. REMOVE FRONT WHEEL OPENING EXTENSION PAD RH

for A25A-FKS: Click here

for A25A-FXS: Click here

for 2GR-FKS: Click here

3. REMOVE NO. 1 ENGINE UNDER COVER

for A25A-FKS: Click here

for A25A-FXS: Click here

for 2GR-FKS: Click here

4. REMOVE SUSPENSION TOWER DAMPER

(a) Remove the 4 bolts and suspension tower damper from the front bumper extension sub-assembly LH and front bumper extension sub-assembly RH.

NOTICE:

Do not extend or compress the damper.

READ NEXT:

 Inspection

INSPECTION PROCEDURE 1. INSPECT SUSPENSION TOWER DAMPER (a) Visually check the suspension tower damper and, if the rod is bent, a leak is found or the damper cannot be installed without extending or c

 Installation

INSTALLATION PROCEDURE 1. INSTALL SUSPENSION TOWER DAMPER (a) Install the suspension tower damper to the front bumper extension sub-assembly LH and front bumper extension sub-assembly RH with the 4 bo

 Installation

INSTALLATION PROCEDURE 1. INSTALL SUSPENSION TOWER DAMPER (a) Install the suspension tower damper to the front bumper extension sub-assembly LH and front bumper extension sub-assembly RH with the 4 bo

SEE MORE:

 Removal

REMOVAL PROCEDURE 1. REMOVE FRONT WHEEL RH Click here 2. REMOVE FRONT FENDER APRON SEAL RH Click here 3. REMOVE V-BANK COVER SUB-ASSEMBLY Click here 4. REMOVE CAMSHAFT TIMING OIL CONTROL SOLENOID ASSEMBLY (for Intake Side of Bank 1) Click here 5. SET NO. 1 CYLINDER TO TDC/COMPRESSION

 Installation

INSTALLATION PROCEDURE 1. INSTALL FUEL PIPE PLUG SUB-ASSEMBLY (a) Install a new O-ring, No. 1 fuel injector back-up ring, No. 2 fuel injector back-up ring and No. 3 fuel injector back-up ring to the fuel pipe plug sub-assembly as shown in the illustration. *1 Fuel Pipe Plug Sub-assembly *2

© 2016-2026 Copyright www.lexguide.net